June 4 Construction Update

Construction has restarted, in compliance with the City of Boston and Commonwealth of Massachusetts' coronavirus protocols. Excavation for footings on the Cummins Highway building continues. The construction team is working on preparing and pouring foundation walls for the townhomes.


Work anticipated, but not limited to, for the weeks of March 12nd – March 25th are as follows:


Building A (820 Cummins Highway)

• Strip footings


Building B (30-32 Regis Road)

• Form foundation walls and Footings

• Strip foundation walls

• Insulate foundation wall


Building C (34 Regis Road)

• Form and pour foundation walls


Building D (38 Regis Road)

• Form and pour foundation walls


Building E (42 Regis Road)

• Back fill foundation and prep underground


6.4.20 2wk Look ahead letter
.pdf
Download PDF • 176KB

2 views0 comments

Recent Posts

See All

Work anticipated, but not limited to, for the weeks of June 22, 2020 to July 4, 2020 are as follows: Building A (820 Cummins Highway) Backfill and prep footings Form footings for elevator and columns

Construction continues at Cote Village, as the general contractor works on preparing footings on all buildings and to pour foundations. Work anticipated, but not limited to, for the weeks of June 15nd

Construction on our Cote Village development in Mattapan area of Boston was temporarily suspended in mid-March to comply with the City of Boston requirements, but we are pleased to be restarting const