October 1 Construction Updates

Work anticipated, but not limited to, for the weeks of July 20, 2020 to August 1, 2020 are as follows:


Building A (820 Cummins Highway)


MU wall for #4

  • Build recharging system

  • Repairing concrete slab

  • Pour retaining wall foundation

  • CMU wall for elevator

  • Install and/or replace steel beams

  • Form footings for elevator and columns

Building B (30-32 Regis Road)

  • Work on utilities lines

  • Frame building

Building C (34 Regis Road)

  • Work on utilities lines

  • Frame building

  • Roof installation

Plumbing, HVAC, Fire Protection rough-in

• Install Windows

• Electrical rough-in

Building D (38 Regis Road)

  • Work on utilities lines

  • Frame building

  • Roof installation

  • Plumbing, HVAC, Fire Protection rough-in

  • Install Windows

  • Electrical rough-in

Building E (42 Regis Road)

  • Work on utilities lines

  • Plumbing, HVAC, Fire Protection rough-in

  • Electrical rough-in

A letter from the general contractor summarizing upcoming work is attached below:

10.1.20 2wk Look ahead letter
.pdf
Download PDF • 179KB