March 12 Construction Update

With demolition completing this week, excavation for footings on the Cummins Highway building has begun. The construction team is working on demolishing the second floor structures. The general contractor anticipates completing abatement and demolition on Regis Road by late March.


Work anticipated, but not limited to, for the weeks of March 12nd – March 25th are as follows:

  • Demolition on 2nd floor of Cummins Highway building to complete

  • Removal of asphalt from 1st floor of Cummins Highway building to complete

  • Demolition of Regis Road Building to complete

  • Demolition of concrete slab and footings of Regis Road building

  • Demolition of concrete slab/excavation of trench for Cummins Highway building plumbing

  • Demolition of slab and excavation of trench for footings and elevator pit

  • Excavation for stairs

  • Start of work on concrete footings


4 views0 comments

Recent Posts

See All

Work anticipated, but not limited to, for the weeks of June 22, 2020 to July 4, 2020 are as follows: Building A (820 Cummins Highway) Backfill and prep footings Form footings for elevator and columns

Construction continues at Cote Village, as the general contractor works on preparing footings on all buildings and to pour foundations. Work anticipated, but not limited to, for the weeks of June 15nd

Construction has restarted, in compliance with the City of Boston and Commonwealth of Massachusetts' coronavirus protocols. Excavation for footings on the Cummins Highway building continues. The const

bottom of page