With abatement on the Cummins Highway building complete, the construction team is working on demolishing the second floor structures. The general contractor anticipates completing abatement and demolition on Regis Road by late March.


Work anticipated, but not limited to, for the weeks of March 2nd – March 13th are as follows:

  • Additional demolition work of Cummins Highway along railroad tracks

  • Onsite monitoring by environmental consultants

  • Remove asphalt from deck of Cummins Highway building

  • Demolition of warehouse along Regis Road (permit received March 3)

  • Demolish concrete slab along Regis Road and excavate for footings

  • Mark out for underground plumbing and footings for Cote Village apartment building (Cummins Highway building)

  • Saw cut concrete for footings for Cote Village apartment building



4 views0 comments

Recent Posts

See All

Work anticipated, but not limited to, for the weeks of June 22, 2020 to July 4, 2020 are as follows: Building A (820 Cummins Highway) Backfill and prep footings Form footings for elevator and columns

Construction continues at Cote Village, as the general contractor works on preparing footings on all buildings and to pour foundations. Work anticipated, but not limited to, for the weeks of June 15nd

Construction has restarted, in compliance with the City of Boston and Commonwealth of Massachusetts' coronavirus protocols. Excavation for footings on the Cummins Highway building continues. The const

bottom of page