Work anticipated, but not limited to, for the weeks of June 29, 2020 to July 11, 2020 are as follows:


Building A (820 Cummins Highway)

  • Form footings for elevator and columns

  • Form curb walls upper deck

  • Work on elevator pit, curb wall on top deck, and stairwell #3 and #4

Building B (30-32 Regis Road)

  • Insulate foundation wall

  • Underground plumbing

  • Start waterlines in the back of the building

Building C (34 Regis Road)

  • Backfill and prep underground

  • Insulate foundation wall

  • Underground plumbing

  • Start waterlines in the back of the building

  • Prepping for slab

Building D (38 Regis Road)

  • Backfill and prep underground

  • Insulate foundation wall

  • Underground plumbing

  • Start waterlines in the back of the building

  • Prepping for slab

  • Work on underslab vapor barrier

Building E (42 Regis Road)

  • Backfill and prep underground

  • Underground plumbing

  • Start waterlines in the back of the building

  • Work on underslab vapor barrier

  • Install rebar and pour slab

A letter from the general contractor summarizing upcoming work is attached below:

6.25.20 2wk Look ahead letter
.pdf
Download PDF • 178KB

Photos of progress so far:


0 views0 comments

Recent Posts

See All

Work anticipated, but not limited to, for the weeks of July 20, 2020 to August 1, 2020 are as follows: Building A (820 Cummins Highway) MU wall for #4 Build recharging system Repairing concrete slab P