top of page
  • POUA

June 11 Construction Updates

Construction continues at Cote Village, as the general contractor works on preparing footings on all buildings and to pour foundations.


Work anticipated, but not limited to, for the weeks of June 15nd – June 26th are as follows:

Building A (820 Cummins Highway)

  • Backfill and prep footings

  • Form footings for elevator and columns

  • Form curb walls upper deck

Building B (30-32 Regis Road)

  • Pour foundation walls

  • Strip foundation walls

  • Insulate foundation wall

  • Underground plumbing

  • Start waterlines in the back of the building

Building C (34 Regis Road)

  • Form and pour foundation walls

  • Backfill and prep underground

  • Insulate foundation wall

  • Underground plumbing

  • Start waterlines in the back of the building

Building D (38 Regis Road)

  • Form and pour foundation walls

  • Backfill and prep underground

  • Insulate foundation wall

  • Underground plumbing

  • Start waterlines in the back of the building

Building E (42 Regis Road)

  • Backfill and prep underground

  • Underground plumbing

  • Start waterlines in the back of the building

6.15.20 2wk Look ahead letter
.pdf
Download PDF • 178KB

0 views0 comments

Recent Posts

See All

Work anticipated, but not limited to, for the weeks of June 22, 2020 to July 4, 2020 are as follows: Building A (820 Cummins Highway) Backfill and prep footings Form footings for elevator and columns

Construction has restarted, in compliance with the City of Boston and Commonwealth of Massachusetts' coronavirus protocols. Excavation for footings on the Cummins Highway building continues. The const

Construction on our Cote Village development in Mattapan area of Boston was temporarily suspended in mid-March to comply with the City of Boston requirements, but we are pleased to be restarting const

bottom of page