June 11 Construction Updates
Construction continues at Cote Village, as the general contractor works on preparing footings on all buildings and to pour foundations.
Work anticipated, but not limited to, for the weeks of June 15nd – June 26th are as follows:
Building A (820 Cummins Highway)
Backfill and prep footings
Form footings for elevator and columns
Form curb walls upper deck
Building B (30-32 Regis Road)
Pour foundation walls
Strip foundation walls
Insulate foundation wall
Underground plumbing
Start waterlines in the back of the building
Building C (34 Regis Road)
Form and pour foundation walls
Backfill and prep underground
Insulate foundation wall
Underground plumbing
Start waterlines in the back of the building
Building D (38 Regis Road)
Form and pour foundation walls
Backfill and prep underground
Insulate foundation wall
Underground plumbing
Start waterlines in the back of the building
Building E (42 Regis Road)
Backfill and prep underground
Underground plumbing
Start waterlines in the back of the building