July 16 Construction Updates

Work anticipated, but not limited to, for the weeks of July 20, 2020 to August 1, 2020 are as follows:
Building A (820 Cummins Highway)
Form footings for elevator and columns
Form curb walls upper deck
Work on elevator pit, curb wall on top deck, and stairwell #3 and #4
Prepping for underpinning
Build groundwater recharge system
Backfill five footings and clean garage area
Delead garage areq
Building B (30-32 Regis Road)
Install rebar, pour slabs and saw cut
Install drainage board and gas barrier
Work on utilities line
Building C (34 Regis Road)
Install rebar, pour slabs and saw cut
install drainage line
Install drainage board and gas barrier
Work on utilities lines
Building D (38 Regis Road)
Install drainage line
Frame building
Work on utilities lines
Building E (42 Regis Road)
Frame building
Work on utilities lines
A letter from the general contractor summarizing upcoming work is attached below: